As part of the Town’s commitment to safer streets, we’re resurfacing the asphalt on the East end of Main Street, from the Town boundary to Victoria Avenue.
New concrete curbs will also be added from Maple Avenue to Victoria and our storm water system, including catch basins will be assessed as part of this project.
Staff estimate this project will take approximately six weeks and traffic control will be in place for the duration.
The road work started on Monday, July 20. Please allow extra time to navigate this part of Town as we expect traffic delays for the duration of the project.
UPDATES:
August 18, 2026: The contractors are starting to work on the curbs and catch basins on East Main, between Maple and Victoria.
They will be starting on the south side of Main near Maple Ave and do not anticipate any disruption to vehicle or pedestrian traffic. They will be working on the side of the street, near the curbs, and appropriate traffic controls (signage, cones, etc.) will be in place.
This work will be ongoing for several weeks and will be followed by the paving of the rest of East Main.
As part of the Town’s commitment to safer streets, we’re resurfacing the asphalt on the East end of Main Street, from the Town boundary to Victoria Avenue.
New concrete curbs will also be added from Maple Avenue to Victoria and our storm water system, including catch basins will be assessed as part of this project.
Staff estimate this project will take approximately six weeks and traffic control will be in place for the duration.
The road work started on Monday, July 20. Please allow extra time to navigate this part of Town as we expect traffic delays for the duration of the project.
UPDATES:
August 18, 2026: The contractors are starting to work on the curbs and catch basins on East Main, between Maple and Victoria.
They will be starting on the south side of Main near Maple Ave and do not anticipate any disruption to vehicle or pedestrian traffic. They will be working on the side of the street, near the curbs, and appropriate traffic controls (signage, cones, etc.) will be in place.
This work will be ongoing for several weeks and will be followed by the paving of the rest of East Main.